    Our scope of work included:

- A Pre-compressor module/ LER/LIR module to be fabricated and installed offshore summer 2013

- Total integration approx. 220 tons

- Approx. 50 ton structural strengthening (complicated Habitat welding)

- Approx. 80 Piping integration tie-ins (some Hyperbaric)

- SAS Integration

- Revamp of existing re-compressors

- Integration of M10 (1024 ton) and LER/LIR  (128 ton) modules